Project Details

Project Timeframe: ​
​Construction is scheduled to begin December 2017 and go through May 31, 2018. 
Planned Improvements: 
  • A more open floor plan with lower shelving and access to natural light
  • A variety of seating styles and reading areas
  • Additional meeting and study rooms
  • Expanded youth areas for toddler/preschool, school-age, and teens
  • Improved security and sight lines throughout the building
  • New computer lab
  • New local history research area
  • New centrally located entrance
  • Upgraded mechanical equipment
  • Updated carpeting and furniture
How much will the project cost?
Approximately $2.1 million. 

How will this be funded?​
$1.9 million is funded through a loan from the City’s Capital Improvement Program. The funds will be paid back to the City over 12 years through the library’s operating funds. About $200,000 will be paid for through library endowments and capital campaign donations. The SPL Foundation is currently fundraising to enhance this project​. For more information (or to donate to the SPL Foundation) click here.
​
Who is working on the project?
The architects are MSR/LHB. The general contractor is Max Gray Construction. LHB will be doing the construction oversight.